The module provides an understanding of the principles of construction laws and its applications. By understanding the basic principle of construction law, the importance of adhering to the specific procedures and notices are emphasized. The next phase is to develop an in-depth knowledge on the application of the law and the remedies available to the parties. Subsequently, students will be able to adopt a systematic approach to analyze disputes and the respective liabilities. Lastly, this module focuses to enhance the students’ knowledge on matters involving contractual claims and its assessment.
TOPICS COVERED:
- Building Contracts – General Principles & Formation of Contract
- The Standard Form of Building Contract
- Collateral Contracts
- Dispute Resolution – Litigation/ Arbitration/Adjudication/Mediation
- Written Documents
- Obligations of parties & QS consultancy agreement
- Breach of Contract – Remedies
- Contractual Claims
- Negligence Claims
- Law relating to payments
- Laws relating to land – National Land Code
- Construction Statutes - UBBL
ASSIGNMENTS DONE:
SEMINAR
TOPIC: Dispute Resolution – Litigation/ Arbitration/Adjudication/Mediation
CASE STUDY
Esso Petroleum Co Ltd v Southport
Corp (1956)
What happened:
The
defendant’s oil tanker ran aground in an estuary partly due to weather
conditions and partly due to carrying a heavy load and a fault in the steering.
The
master
discharged 400 tons of oil in order to free the tanker.
The
oil
drifted onto the claimant’s land including a marine lake which it had to close
until it had been cleaned at a substantial cost to the claimant.
The
claimant
brought an action in negligence and nuisance.
The
trial
judge found for the defendant and the claimant appealed.
It was held that:
Appeal
allowed (Morris LJ dissenting),
the
defendant was liable in negligence and public nuisance.
The Court said on private nuisance:
“In
order to support an action on the case for a private nuisance, the defendant
must have used his own land or some other land in such a way as injuriously to
affect the enjoyment of the plaintiff's land. The ground of responsibility is
the possession and control of the land from which the nuisance proceeds.
Applying this principle, it is clear that the discharge of oil was not a
private nuisance, because it did not involve the use by the defendants of any
land, but only of a ship at sea.”
Asiapools (M) Sdn Bhd v IJM Construction Sdn Bhd & ORS (2010)
Facts:
The
plaintiff
was the nominated sub-contractor to build, inter alia, a swimming pool for a
161-unit condominium in Seremban.
The
defendant,
the main contractor had earlier entered into a main contract with the developer
(“the employer”), Ng Chee Yew Sdn Bhd, to build the condominium.
The
plaintiff
had completed the swimming pool, but has not been paid fully by the defendant,
as the employer had not paid the defendant.
Pursuant
to
the main contract, the defendant has commenced an action against the employer
to recover the sum of RM1,749,762.08.
Under
the
sub-contract, the plaintiff had filed the claim in the sessions court for the
unpaid sum of RM212,989.25.
Appeal
Parties
are
referred to in their capacities in the sessions court.
The
Kuala
Lumpur sessions court had allowed the plaintiff’s claim with costs against the
defendant.
The defendant’s appeal to the High Court was allowed with costs.
The
High
Court made a further order that the judgment sum of RM271,458.29, paid by the
defendant to the plaintiff, be returned to the defendant, together with
interest at 8% p.a.
Court’s Decision
The
plaintiff
is then appealed to Court of Appeal.
No comments:
Post a Comment